Bihar has taken its biggest step yet into India’s artificial intelligence race. CtrlS Datacenters, Asia’s largest Rated-4 data centre operator, signed a memorandum of understanding with the Bihar government on Friday to build a 150 MW hyperscale AI factory in the state, backed by an investment of Rs 10,000 crore.
The agreement was signed in Patna, where a CtrlS delegation led by chief operating officer Sudarshan Malpani met officials of the state’s Department of Industries. Bihar Chief Minister Samrat Choudhary was present at the signing, underlining how much the state government wants this project to move fast.
The facility is expected to begin commercial operations by 2029-30 and will create 400 direct jobs, with 100 roles on site and another 300 with the customers who host their systems there. It will come up on a 100-acre plot close to a 220/400 kV power substation, preferably in or around Patna, so the power-hungry AI hardware has the grid connection it needs from day one.
From a letter of intent to a signed deal
Friday’s MoU turns a promise made last month into a formal commitment. On October 13, CtrlS signed a letter of intent with the Bihar government for the same Rs 10,000 crore, 150 MW project, on the same day it inaugurated its Rs 400 crore data centre in Patna’s Patliputra Industrial Area.
That Patna facility currently offers 12 MW of IT load and serves enterprises, government institutions, hyperscalers and technology businesses across Bihar and eastern India. The new AI factory, at 150 MW, will be more than twelve times its size, a measure of how quickly the company expects demand for AI computing to grow.
CtrlS founder and chief executive Sridhar Pinnapureddy has said the company is committed to strengthening Bihar’s digital infrastructure and building an IT ecosystem through future-ready data centres designed for hyperscalers, enterprises and startups. He has also thanked the state government for a policy environment and incentives that supported the investment.
The facility in numbers
- Investment: Rs 10,000 crore, roughly 1 billion US dollars
- Capacity: 150 MW hyperscale AI factory
- Jobs: 400 direct jobs, 100 on site and 300 with hosted customers
- Land: 100 acres near a 220/400 kV substation, in or around Patna
- Target: commercial operations by 2029-30
- Existing base: Rs 400 crore Patna data centre with 12 MW IT load
CtrlS began operations in 2007 and runs 19 data centres across nine markets in India. The company plans to build more than 4.4 GW of data centre capacity by 2030, and the Bihar project is a significant part of that push into cities beyond the established hubs of Mumbai, Chennai, Hyderabad and Noida.

Why it matters
Data centres are where the AI boom becomes concrete. Every chatbot answer, every AI-generated image and every machine learning model trained for Indian languages runs on racks of graphics processors inside facilities like the one CtrlS plans for Bihar, and India is racing to host more of that computing at home rather than renting it from abroad.
For Bihar, the deal matters in three specific ways. First, it puts the state on the AI infrastructure map, a list long dominated by a handful of metros. Second, the 400 jobs are only the direct count; data centres pull in power engineers, network specialists, security staff and maintenance crews, and they give local technology graduates a reason to build careers without leaving the state. Third, a large AI-ready facility in Patna lets state government departments, universities and local businesses run heavy digital workloads close to home, instead of depending entirely on infrastructure hundreds of kilometres away.
There is also a timing angle. Under the government’s IndiaAI Mission, Indian cloud providers already host more than 44,000 graphics processing units, and demand for AI computing keeps climbing. A 150 MW facility that opens in 2029-30 will arrive just as that demand is expected to peak, provided the land, power and construction timelines hold. The MoU is a commitment, not a finished building, and the next milestones to watch are the land allotment and the start of construction.
What happens next
The immediate next step is finalising the 100-acre site near the substation, after which construction can begin. CtrlS will also need to line up power supply agreements and the customers who will fill the racks once the facility opens. If the 2029-30 target holds, Bihar will have one of eastern India’s largest AI computing facilities within four years of the agreement.
For now, the MoU signals that India’s data centre map is widening. The same week, the country’s first deep-tech hub was announced at IIT Kanpur’s Noida campus, and chip and AI infrastructure stories are dominating technology news. Bihar’s Rs 10,000 crore bet is part of that wider shift, and it is the largest single technology investment the state has attracted.
FAQs
What did CtrlS sign with the Bihar government?
A memorandum of understanding to invest Rs 10,000 crore in a 150 MW hyperscale AI-ready data centre in Bihar, signed in Patna on November 20, 2026.
How many jobs will the project create?
About 400 direct jobs, with 100 roles on site and 300 with the customers hosted at the facility.
When will the data centre start operations?
CtrlS aims for commercial operations by 2029-30.
Where will the facility be built?
On a 100-acre plot close to a 220/400 kV power substation, preferably in or around Patna.
Is this CtrlS’s first project in Bihar?
No. The company inaugurated a Rs 400 crore data centre in Patna in October 2026 and signed a letter of intent for the AI factory at the same time. Friday’s MoU formalises that plan.
Bihar’s AI ambitions now have a signed agreement behind them. The test, as with every mega project, will be how quickly the paperwork turns into construction, and then into servers humming in Patna.